[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52512":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52512,53,2,"多选题","建设单位在招标和施工过程中不得（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","要求修改设计文件",false,{"key":16,"text":17,"correct":18},"B","明示或暗示设计单位违反工程建设强制性标准",true,{"key":20,"text":21,"correct":18},"C","迫使承包方以低于成本的价格竞标",{"key":23,"text":24,"correct":18},"D","明示或暗示施工单位使用不合格的建筑材料",{"key":26,"text":27,"correct":18},"E","任意压缩合理工期","BCDE","建设单位的质量责任，包括例如：①建设工程发包单位不得迫使承包方以低于成本的价格竞标，不得任意压缩合理工期。建设单位不得明示或者暗示设计单位或者施工单位违反工程建设强制性标准，降低建设工程质量。故BCE三项正确。②建设单位不得明示或者暗示施工单位使用不合格的建筑材料、建筑构配件和设备。故D项正确。③建设单位应当将施工图送审查机构审查。施工图未经审查批准的，不得使用。施工图退建设单位后，建设单位应当要求原勘察设计企业进行修改，并将修改后的施工图送原审查机构复审。故A项错误。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]