[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52503":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52503,53,2,"多选题","与传统的DBB模式相比，工程总承包（DB\u002FEP C）模式的不足有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","道德风险高",true,{"key":16,"text":17,"correct":14},"B","建设单位前期工作量大",{"key":19,"text":20,"correct":14},"C","工程总承包单位报价高",{"key":22,"text":23,"correct":24},"D","设计与施工协调困难",false,{"key":26,"text":27,"correct":24},"E","工程的责任主体较多","ABC","工程总承包（DB\u002FEPC）模式的不足包括：①道德风险高；②建设单位前期工作量大；③工程总承包单位报价高。DBB模式的不足包括：①工程设计、招标、施工按顺序依次进行，建设周期长；②而且由于施工单位无法参与工程设计，设计与施工协调困难，容易产生设计变更，可能使建设单位利益受损。此外，由于工程的责任主体较多，一旦工程出现问题，建设单位将分别面对不同参与方，容易出现互相推诿，协调工作量大。DE两项属于DBB模式的不足。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]