[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52489":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52489,53,2,"多选题","下列属于建设单位主要合同关系的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程分包合同",false,{"key":16,"text":17,"correct":18},"B","工程承包合同",true,{"key":20,"text":21,"correct":18},"C","工程勘察设计合同",{"key":23,"text":24,"correct":18},"D","工程咨询监理合同",{"key":26,"text":27,"correct":14},"E","劳务分包合同","BCD","建设单位的主要合同关系包括：①工程勘察设计合同；②工程承包合同；③材料设备采购合同；④工程咨询监理或项目管理合同；⑤贷款合同；⑥其他合同。承包单位的主要合同关系包括：①工程分包合同；②劳务分包合同；③材料设备采购合同；④运输合同；⑤加工合同；⑥租赁合同；⑦保险合同。AE两项属于承包单位的主要合同关系。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]