[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52376":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52376,53,2,"多选题","下列房地产开发活动中，属于建设阶段工作任务的有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","开发场地的工程勘测",false,{"key":16,"text":17,"correct":14},"B","项目发包",{"key":19,"text":20,"correct":21},"C","项目施工建设管理",true,{"key":23,"text":24,"correct":21},"D","项目控制与工程监理",{"key":26,"text":27,"correct":21},"E","项目竣工验收","CDE","建设阶段是将前期阶段的各项方案和计划以及项目开发过程中所涉及的人力、材料、机械设备、资金等资源集中于开发地块上和特定的时间段上，进行正式施工建设的活动。这一阶段的工作任务主要是进行项目施工建设管理、项目控制、工程监理、项目竣工验收和交付使用。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]