[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52374":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52374,53,2,"多选题","房屋建筑安装工程直接费是由( )及其他直接费构成。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程量",true,{"key":16,"text":17,"correct":14},"B","材料耗费",{"key":19,"text":20,"correct":21},"C","施工管理费",false,{"key":23,"text":24,"correct":21},"D","投资利息",{"key":26,"text":27,"correct":14},"E","机械台班","ABE","房屋建筑安装工程直接费用包括工程量、工时、机械台班、材料耗费、工程其他费用支出。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]