[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52292":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52292,53,2,"多选题","为保证施工项目目标的顺利实施，项目开工前建设工程监理单位必须进行充分的施工准备，其主要内容大致可分为( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工部署",false,{"key":16,"text":17,"correct":18},"B","审查施工单位选择分包单位的资质",true,{"key":20,"text":21,"correct":18},"C","参与设计单位向施工单位的设计交底",{"key":23,"text":24,"correct":14},"D","工序交接",{"key":26,"text":27,"correct":18},"E","审查施工组织设计","BCE","施工准备阶段建设监理的主要任务：①审查施工单位选择分包单位的资质；②监督检查施工单位质量保证体系及安全技术措施，完善质量管理程序与制度；③参与设计单位向施工单位的设计交底；④审查施工组织设计；⑤在单位工程开工前检查施工单位的复测资料；⑥对重点工程部位的中线和水平控制进行复查；⑦审批一般单项工程和单位工程的开工报告。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]