[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52285":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52285,53,2,"多选题","工程成本可分为( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","实际成本降低额",false,{"key":16,"text":17,"correct":18},"B","计划成本",true,{"key":20,"text":21,"correct":18},"C","实际成本",{"key":23,"text":24,"correct":18},"D","预算成本",{"key":26,"text":27,"correct":14},"E","概算成本","BCD","工程成本管理的工程成本类型分为：①预算成本；②计划成本；③实际成本。其中预算成本是反映各地区建筑业的平均成本水平；计划成本是指施工单位根据计划期的有关资料，在实际成本发生前期先计算的成本；实际成本是工程施工项目在报告期内实际发生的各项生产费用的总和。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]