[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52284":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52284,53,2,"多选题","要保证工程成本的真实性和准确性，应( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","努力提高业务人员的业务素质和思想素质",true,{"key":16,"text":17,"correct":18},"B","实行项目成本目标分解归口管理",false,{"key":20,"text":21,"correct":14},"C","加强业务部门之间的联系和协调",{"key":23,"text":24,"correct":14},"D","做好与成本有关的管理和消耗台账",{"key":26,"text":27,"correct":18},"E","落实项目目标成本责任制","ACD","要保证成本的真实性、准确性需做到：①要努力提高业务人员的业务素质和思想素质；②要加强业务部门之间的联系和协调；③要做好统计报表(预算收入)台账，同期计划成本台账，材料采购台账，材料消耗台账，外包工结账及用工分析台账，机械租赁、周转材料租赁台账，其他与成本有关的消耗台账。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]