[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52279":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52279,53,2,"多选题","施工过程中控制工程成本的方法主要有( )",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","编制并落实工程成本计划",true,{"key":16,"text":17,"correct":14},"B","建立月度资金收支计划管理制度",{"key":19,"text":20,"correct":21},"C","控制投标报价的让利幅度",false,{"key":23,"text":24,"correct":21},"D","及时办理经济技术签证",{"key":26,"text":27,"correct":14},"E","实施施工成本跟踪考核","ABE","成本控制应结合施工过程中的不同情况，采取与之相适应的控制手段和控制方法。工程成本控制的方法有：①以成本计划控制工程项目施工成本支出；②建立月度资金收支计划，进行成本控制；③实施对施工成本跟踪考核，进行动态控制。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]