[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52277":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52277,53,2,"多选题","工程项目成本控制程序的环节有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","制定控制标准",true,{"key":16,"text":17,"correct":18},"B","建立控制制度",false,{"key":20,"text":21,"correct":14},"C","实施成本监督",{"key":23,"text":24,"correct":14},"D","确定成本差异",{"key":26,"text":27,"correct":14},"E","消除成本差异","ACDE","工程项目成本控制是指项目在施工过程中，通过成本控制，使之最终实现甚至超过预期的成本目标。工程成本控制的程序包括：①制定工程成本控制标准；②实施成本监督；③确定差异；④消除差异。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]