[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52267":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52267,53,2,"多选题","分部分项工程量清单包括( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","项目编码",true,{"key":16,"text":17,"correct":14},"B","项目名称",{"key":19,"text":20,"correct":14},"C","计量单位",{"key":22,"text":23,"correct":14},"D","工程计量",{"key":25,"text":26,"correct":27},"E","工程量计算规则",false,"ABCD","分部分项工程量清单包括：①项目编码；②项目名称；③项目特征；④计量单位；⑤工程计量。@##",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]