[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52266":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52266,53,2,"多选题","下列关于工程价款的调整,说法正确的是( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","招标工程在投标截止日前28天之后因国家法律. 法规发生变化影响到工程造价的，应按规定调整合同价款。",true,{"key":16,"text":17,"correct":18},"B","若施工图纸与工程量清单项目特征描述不符，应按工程量清单项目特征确定的综合单价结算",false,{"key":20,"text":21,"correct":18},"C","因不可抗力事件导致的第三方人员伤亡，由承包人承担责任",{"key":23,"text":24,"correct":18},"D","因不可抗力事件导致的施工现场清理费用，由承包人承担",{"key":26,"text":27,"correct":14},"E","若施工期内市场价格波动超出一定幅度时，应按合同约定调整工程价款","AE","若施工图纸与工程量清单项目特征描述不符，应按新的项目特征确定综合单价；因不可抗力事件导致的第三方人员伤亡和财产损失，施工现场清理、修复费用，应由发包人承担。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]