[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52265":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52265,53,2,"多选题","工程量清单的主要组成部分有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","分部分项工程量清单计价表",false,{"key":16,"text":17,"correct":18},"B","分部分项工程量清单",true,{"key":20,"text":21,"correct":18},"C","措施项目清单",{"key":23,"text":24,"correct":18},"D","其他项目清单",{"key":26,"text":27,"correct":14},"E","计算规则","BCD","工程量清单是表现拟建工程的分部分项工程项目、措施项目、其他项目、规费项目和税金项目的名称和相应数量的明细清单。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]