[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52261":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52261,53,2,"多选题","下列工人工作时间中，属于有效工作时间的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","休息时间",false,{"key":16,"text":17,"correct":18},"B","基本工作时间",true,{"key":20,"text":21,"correct":18},"C","准备与结束工作时间",{"key":23,"text":24,"correct":14},"D","停工时间",{"key":26,"text":27,"correct":18},"E","辅助工作时间","BCE","必须消耗的时间分为有效工作时间、休息时间、不可避免的中断时间。其中有效工作时间分为基本工作时间、准备与结束工作时间、辅助工作时间。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]