[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52259":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52259,53,2,"多选题","工人工作时间中所必须消耗的时间有( )时间。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","休息",true,{"key":16,"text":17,"correct":18},"B","施工本身造成的停工",false,{"key":20,"text":21,"correct":18},"C","停工",{"key":23,"text":24,"correct":14},"D","有效工作时间",{"key":26,"text":27,"correct":14},"E","不可避免中断","ADE","工人工作时间按其消耗的性质，基本可以分为两大类：必须消耗的时间和损失时间。必须消耗的时间是工人在正常施工条件下，为完成一定产品(工作任务)所消耗的时间，它包括有效工作时间、休息和不可避免中断时间。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]