[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52242":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52242,53,2,"多选题","下列时间中，属于工人工作时间中必须消耗时间的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","有效工作时间",true,{"key":16,"text":17,"correct":18},"B","停工时间",false,{"key":20,"text":21,"correct":14},"C","休息时间",{"key":23,"text":24,"correct":18},"D","偶然时间",{"key":26,"text":27,"correct":14},"E","不可避免的中断时间","ACE","必须消耗时间包括有效工作时间、不可避免的中断时间和休息时间。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]