[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52231":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52231,53,2,"多选题","施工阶段工程质量控制的内容和措施包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","编制施工组织设计",false,{"key":16,"text":17,"correct":18},"B","严格进行材料试验",true,{"key":20,"text":21,"correct":14},"C","组织技术交底",{"key":23,"text":24,"correct":18},"D","实施工序质量监控",{"key":26,"text":27,"correct":18},"E","积累施工技术资料","BDE","编制施工组织设计、组织技术交底属于施工准备阶段工作质量控制的内容和措施。在施工阶段施工质量控制的内容和措施主要有：严格进行材料、构配件试验和施工试验；实施工序质量监控；重视设计变更管理；加强成品保护；积累工程施工技术资料等 A、C属于准备阶段的内容",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]