[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52212":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52212,53,2,"多选题","为保证工程项目进度目标的顺利实现，应开展的主要工作有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","检查各层次的进度计划，形成严密的计划保证系统",true,{"key":16,"text":17,"correct":18},"B","控制外部环境和条件变化",false,{"key":20,"text":21,"correct":14},"C","签订责任状",{"key":23,"text":24,"correct":14},"D","做好工程进度记录. 填写工程进度统计表",{"key":26,"text":27,"correct":14},"E","做好工程建设中的调度工作","ACDE","为使工程的实施按进度计划编制的时间逐步进行，保证进度目标的顺利实现，应做好以下工作：①检查各层次的进度计划，形成严密的计划保证系统；②层层签订责任状或下达施工任务书；③做好工程进度记录、填写工程进度统计表；④做好工程建设中的调度工作。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]