[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52207":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52207,53,2,"多选题","工程实际进度与计划进度的比较方法主要有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","横道图比较法",true,{"key":16,"text":17,"correct":18},"B","直方图比较法",false,{"key":20,"text":21,"correct":14},"C","S型曲线比较法",{"key":23,"text":24,"correct":18},"D","工程预算比较法",{"key":26,"text":27,"correct":14},"E","网络计划图上比较法","ACE","工程实际进度与计划进度的比较方法主要有横道图比较法、S型曲线比较法、网络计划图上比较法。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]