[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52204":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52204,53,2,"多选题","下列选项中，属于工程进度管理组织措施的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建立进度管理工作制度",true,{"key":16,"text":17,"correct":18},"B","采取加快工程进度的施工方法",false,{"key":20,"text":21,"correct":18},"C","合同工期与进度计划的协调",{"key":23,"text":24,"correct":14},"D","确定进度目标及责任落实",{"key":26,"text":27,"correct":14},"E","分析影响进度目标实现的风险因素","ADE","进度管理的组织措施主要包括：①建立相应的进度管理组织机构，并由专门的工作部门和符合进度控制岗位资格的专人负责进度控制工作；②进度目标的分析、论证、分解和落实到各层次或各部门的进度管理人员、明确其具体任务和职责分工，形成进度控制目标体系；③编制进度计划和进度控制的工作流程、建立进度管理工作制度等，如进度检查的时间、方法、进度协调会议举行的时间、地点、内容及参与人员等；④分析影响进度目标实现的干扰和风险因素。B选项属于技术措施；C选项属于合同措施。加强工程风险管理与索赔管理属于合同措施。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]