[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52203":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52203,53,2,"多选题","施工段是表达流水施工的空间参数。合理划分施工段的基本要求有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","每个施工过程在各个施工段上的劳动量均应相等",false,{"key":16,"text":17,"correct":18},"B","施工段的分界线应尽可能设在对结构整体性影响较小的部位",true,{"key":20,"text":21,"correct":18},"C","每个施工段要有足够的工作面，以充分发挥专业工人和机械设备的生产效率",{"key":23,"text":24,"correct":14},"D","每个施工段要有足够的工作面，以满足同一施工段内组织多个专业工作队同时施工的要求",{"key":26,"text":27,"correct":18},"E","施工段的数目应与主导施工过程相协调","BCE","合理划分施工段的基本要求有：①有利于保持结构的整体性，为了保证拟建工程项目结构整体的完整性，施工段的分界线尽可能与结构的自然界线相一致，或设在对结构整体性影响较小的门窗洞口等部位；②各施工段的劳动量相等或大致相等；③要有足够的工作面，施工段的大小应保证工人施工有足够的作业空间(工作面)，以便充分发挥专业工人和机械设备的生产效率；④施工段的数目应与主导施工过程相协调，施工段的划分宜以主导施工过程(即对整个流水施工起决定性作用的施工过程)为主，形成工艺组合，合理确定施工段的数目；⑤组织多层建筑物流水施工时，施工段数应大于或等于施工过程数。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]