[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52200":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52200,53,2,"多选题","与运用横道图编制进度计划相比，运用网络图编制进度计划的优越性主要有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","编制方法简单明了",false,{"key":16,"text":17,"correct":18},"B","能全面清洗的表达各项工作之间相互制约. 相互依赖的关系。",true,{"key":20,"text":21,"correct":18},"C","可采用计算机技术及相关软件对进度计划实行动态管理",{"key":23,"text":24,"correct":18},"D","能够进行各种时间参数的计算并对进度计划进行优化",{"key":26,"text":27,"correct":14},"E","可形象直接地反映进度与资源消耗量之间的关系","BCD","E选项属于横道图的优点，网络图的缺点，但网络图可以采用时标网络计划解决这一问题。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]