[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52196":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52196,53,2,"多选题","根据工程项目计划管理的需要，工程项目进度计划应包括( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程项目年度计划",true,{"key":16,"text":17,"correct":14},"B","工程项目前期工作计划",{"key":19,"text":20,"correct":21},"C","成本控制计划",false,{"key":23,"text":24,"correct":21},"D","资源安排计划 .",{"key":26,"text":27,"correct":14},"E","工程项目建设总进度计划","ABE","工程进度计划系统主要包括：①工程项目前期工作计划；②工程项目总进度计划；③工程项目年度计划；④单项工程或单位工程进度计划；⑤分部(分项)工程进度计划。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]