[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52194":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52194,53,2,"多选题","在项目管理信息系统中，构建进度控制与管理子系统采用的基本方法有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","项目结构分解法",false,{"key":16,"text":17,"correct":14},"B","工作结构分解法",{"key":19,"text":20,"correct":21},"C","计划进度与实际进度的比较方法",true,{"key":23,"text":24,"correct":21},"D","网络计划技术",{"key":26,"text":27,"correct":14},"E","系统分析法","CD","进度控制与管理子系统的基本方法是网络计划技术、计划进度与实际进度的比较方法。计划进度和实际进度的比较可通过工作的开始时间、工作的完成时间、完成率、形象进度的比较来实现。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]