[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52187":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52187,53,2,"多选题","施工阶段业主方的质量控制工作主要包括( ).",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","组织并完成施工现场的“三通一平”工作",true,{"key":16,"text":17,"correct":14},"B","组织图纸会审核技术交底",{"key":19,"text":20,"correct":21},"C","审查编制施工组织设计文件",false,{"key":23,"text":24,"correct":14},"D","审查分包单位资质条件",{"key":26,"text":27,"correct":21},"E","组织原材料. 半成品和设备的现场检查. 验收和测试","ABD","审查进场原材料、构配件和设备等的出厂证明、技术合格证、质量保证书以及检验报告是业主方的质量控制工作，答案E属于施工方的质量控制工作。C选项应为审查批准施工组织设计文件。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]