[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52069":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52069,53,2,"多选题","在工程施工过程中，施工单位不得( ).",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","分包工程",false,{"key":16,"text":17,"correct":14},"B","租赁施工机械",{"key":19,"text":20,"correct":21},"C","使用未经检验的建筑材料",true,{"key":23,"text":24,"correct":21},"D","自行进行隐蔽工程验收",{"key":26,"text":27,"correct":21},"E","擅自修改工程设计","CDE","考查施工单位的质量责任。总承包单位可以依法将建设工程分包；施工单位不得擅自修改工程设计，不得偷工减料；对建筑材料或构配件，未经检验或者检验不合格的，不得使用；隐蔽工程在隐蔽前，必须通知建设单位和建设工程质量监督机构。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]