[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52051":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52051,53,2,"多选题","工程施工组织设计中主要包括( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","施工程序、施工顺序",true,{"key":16,"text":17,"correct":14},"B","保证质量、安全生产",{"key":19,"text":20,"correct":14},"C","季节性施工",{"key":22,"text":23,"correct":24},"D","进度保证及现场管理",false,{"key":26,"text":27,"correct":14},"E","防止环境污染","ABCE","考查施工准备阶段的质量控制。 施工组织设计中，对质量控制起主要作用的是施工方案，主要包括施工工序的安排、流水段的划分、主要项目的施工方法、施工机械的选择，以及保证质量、安全施工、冬季和雨季施工、污染防止等方面的预控方法和针对性的技术组织措施。 D为干扰选项。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]