[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52034":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52034,53,2,"多选题","下列措施中，属于进度管理合同措施的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","实行分段设计、分段发包、分段施工、缩短建设工期",true,{"key":16,"text":17,"correct":18},"B","建立进度管理工作制度",false,{"key":20,"text":21,"correct":14},"C","协调合同工期与进度计划的关系",{"key":23,"text":24,"correct":18},"D","确定进度目标及责任落实",{"key":26,"text":27,"correct":14},"E","加强索赔管理","ACE","进度管理的合同措施主要包括：①推行CM承发包模式，对工程实行分段设计、分段发包、分段施工，以缩短建设工期；②加强合同管理、协调合同工期与进度计划之间的关系；③严格控制合同变更；④加强风险管理与索赔管理等。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]