[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52032":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52032,53,2,"多选题","在工程实施过程中，进度拖延的原因通常有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","制定工期及相关计划的失误",true,{"key":16,"text":17,"correct":14},"B","工程变更",{"key":19,"text":20,"correct":21},"C","未采取加快进度的技术措施",false,{"key":23,"text":24,"correct":14},"D","管理过程中的失误",{"key":26,"text":27,"correct":14},"E","资金不到位和停工待料","ABDE","进度拖延的原因通常有：制定工期及相关计划的失误、计划工期或计划进度超出实现的可能性、不利自然条件的影响、管理过程中的失误、工程变更、资金不到位、停工待料等等。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]