[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52031":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52031,53,2,"多选题","流水施工组织方式具有的特点有()。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","充分利用工作面，施工工期较短",true,{"key":16,"text":17,"correct":14},"B","为文明施工和进行现场的科学管理创造有利条件",{"key":19,"text":20,"correct":14},"C","专业队及其工人能连续作业",{"key":22,"text":23,"correct":14},"D","有利于资源供应的组织工作",{"key":25,"text":26,"correct":27},"E","具有很好的稳定性和时效性",false,"ABCD","流水施工组织方式具有以下特点： ①充分利用了工作面，争取了时间，相对依次施工而言，施工工期较短； ②专业工作队能够连续施工、相邻专业工作队之间进行了最大限度的搭接施工； ③各工作队实现了专业化施工，有利于提高工人的技术水平和劳动效率，能更好地保证工程质量； ④单位时间投入的劳动力和机具设备等资源较为均衡，有利于资源供应的组织； ⑤为文明施工和现场的科学管理创造了有利条件。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]