[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-52002":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},52002,53,2,"多选题","设计阶段投资控制的主要工作包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","在可行性研究的基础上，进行项目总投资目标的分析和论证",false,{"key":16,"text":17,"correct":18},"B","审核施工图预算，必要时调整总投资计划",true,{"key":20,"text":21,"correct":18},"C","编制项目总投资分解规划，并在设计过程中控制其执行",{"key":23,"text":24,"correct":18},"D","采用价值工程方法，在充分满足功能的条件考虑进一步挖掘节约投资的潜力",{"key":26,"text":27,"correct":14},"E","审核招标文件和合同文件中有关投资的条款","BCD","选项A属于设计前准备阶段投资控制的主要工作。E选项属于工程发包与物资采购阶段投资控制的主要工作。",{"id":6,"name":31,"category":32,"favorite":33},"(初级)建筑与房地产经济","经济金融",0]