[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51920":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},51920,53,1,"单选题","工程项目管理信息系统（PMIS）包括的子系统是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投资控制、进度控制、质量控制、建设控制、HSE管理",false,{"key":16,"text":17,"correct":18},"B","投资控制、进度控制、质量控制、HSE管理、合同管理",true,{"key":20,"text":21,"correct":14},"C","合同管理、HSE管理、资源控制、过程控制、进度控制",{"key":23,"text":24,"correct":14},"D","合同管理、HSE管理、界面控制、过程控制、进度控制","工程项目管理信息系统结构主要由投资（成本）控制、进度控制、质量控制、HSE（职业健康、安全、环境）管理、合同管理五个子系统组成，五个子系统共享数据库，既相对独立又互有联系。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]