[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51912":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},51912,53,1,"单选题","施工单位在施工组织设计中应当编制（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","安全技术措施和分部分项工程专项施工方案",false,{"key":16,"text":17,"correct":18},"B","安全技术措施和施工现场临时用电方案",true,{"key":20,"text":21,"correct":14},"C","分部分项工程专项施工方案和安全验算结果",{"key":23,"text":24,"correct":14},"D","分部分项工程专项施工方案和施工现场临时用电方案","施工单位应当在施工组织设计中编制安全技术措施和施工现场临时用电方案，对达到一定规模的危险性较大的分部分项工程编制专项施工方案，并附具安全验算结果。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]