[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51895":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},51895,53,1,"单选题","建设单位编制（也可委托咨询单位编制）的进度计划不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程项目前期工作计划",false,{"key":16,"text":17,"correct":14},"B","工程建设总进度计划",{"key":19,"text":20,"correct":14},"C","工程项目年度计划",{"key":22,"text":23,"correct":24},"D","工程项目月度计划",true,"建设单位编制（或委托咨询单位编制）的进度计划包括：①工程项目前期工作计划，指对工程项目策划、可行性研究及其评估、决策审批或核准\u002F备案等工作进度的安排；②工程建设总进度计划，指工程项目决策立项后，对工程项目从开始建设（设计、施工准备）至竣工投产（动用）全过程的统一部署；③工程项目年度计划，指依据工程建设总进度计划和批准的设计文件，按年编制的进度计划。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]