[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51891":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},51891,53,1,"单选题","某工程项目的屋面工程可以分解为 A、 B、 C、D四个施工过程组织流水作业，各施工过程的流水节拍均为3天，其中 C、D工作之间有1天技术间歇时间，若取施工段数等于施工过程数，则屋面工程的流水施工工期是（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","13",false,{"key":16,"text":17,"correct":14},"B","18",{"key":19,"text":20,"correct":21},"C","22",true,{"key":23,"text":24,"correct":14},"D","25","由已知条件可得：t1＝t2＝t3＝t4＝3（天）。计算过程如下： ①取施工段：m＝n＝4（段）。 ②确定流水步距：K＝t＝3（天）。 ③计算工期：T＝（m＋n－1）K＋∑Z－∑C＝（4＋4－1）×3＋1－0＝22（天）。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]