[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51889":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},51889,53,1,"单选题","某工程项目的基础工程可以分解为 A、 B、 C、D四个施工过程，各施工过程的流水节拍均为3天，施工中分四个施工段组织流水作业，其中 C、D工作之间需要2天技术间歇时间，则其流水施工工期是（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","21",false,{"key":16,"text":17,"correct":18},"B","23",true,{"key":20,"text":21,"correct":14},"C","25",{"key":23,"text":24,"correct":14},"D","27","全等节拍流水施工也称为等节奏流水施工或固定节拍流水施工，是指各个施工过程在各个施工段上的流水节拍彼此相等的流水施工组织方式。由已知条件：t1＝t2＝t3＝t4＝t＝3（天）。因此，本工程宜组织全等节拍流水施工。计算过程如下： ①取施工段：m＝n＝4（段）。 ②确定流水步距：K＝t＝3（天）。 ③计算工期：T＝（m＋n－1）K＋∑Z－∑C＝（4＋4－1）×3＋2－0＝23（天）",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]