[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51886":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},51886,53,1,"单选题","下列工程进度控制措施中，属于经济措施的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","评选设计方案",false,{"key":16,"text":17,"correct":14},"B","编制进度管理目标体系",{"key":19,"text":20,"correct":14},"C","选择合同结构",{"key":22,"text":23,"correct":24},"D","编制资源需求计划",true,"进度控制的经济措施主要包括：编制与进度计划相协调的资源需求计划（包括资金需求计划和人、材、机等资源需求计划），以反映工程实施各时段所需要的资源，保证进度计划实现的可能性；落实实现进度目标的建设资金，保证工程项目用款能及时拨付；对应急赶工应给予相应的赶工费用补偿、对工期超前或延误建立相应的奖惩制度。A项属于技术措施；B项属于组织措施；C项属于合同措施。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]