[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51884":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},51884,53,1,"单选题","关于工程进度控制措施的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程进度控制的主要措施是组织和技术措施",false,{"key":16,"text":17,"correct":14},"B","经济和合同措施是工程进度控制措施中的关键措施",{"key":19,"text":20,"correct":14},"C","工程进度控制措施在当代主要是指信息管理措施",{"key":22,"text":23,"correct":24},"D","工程进度控制措施包括组织、技术、经济、合同和信息管理措施",true,"为确保工程进度目标的顺利实现，必须制订工程进度控制措施。通常采取的进度控制措施有组织措施、技术措施、经济措施、合同措施和信息管理措施。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]