[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51883":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},51883,53,1,"单选题","用来安排自勘察设计准备开始至施工图设计完成的整个勘察设计过程中所包含的各阶段工作进度，以确保勘察设计进度控制总目标的实现的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","勘察设计总进度计划",true,{"key":16,"text":17,"correct":18},"B","勘察设计作业进度计划",false,{"key":20,"text":21,"correct":18},"C","阶段性勘察设计进度计划",{"key":23,"text":24,"correct":18},"D","勘察工作进度计划","勘察设计单位编制的进度计划包括：①勘察设计总进度计划；②阶段性勘察设计进度计划；③勘察设计作业进度计划。其中，勘察设计总进度计划主要用来安排自勘察设计准备开始至施工图设计完成的整个勘察设计过程中所包含的各阶段工作进度，以确保勘察设计进度控制总目标的实现。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]