[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51880":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},51880,53,1,"单选题","通过压缩关键工作的持续时间来调整进度计划，以下属于组织措施是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","增加工作面，组织更多的施工队伍",true,{"key":16,"text":17,"correct":18},"B","实施强有力的组织调度",false,{"key":20,"text":21,"correct":18},"C","对所采用的技术措施给予经济补偿",{"key":23,"text":24,"correct":18},"D","采用更先进的施工机械","通过缩短网络计划中关键线路上工作（关键工作）的持续时间来缩短工期，具体措施包括：组织措施、技术措施、经济措施和其他配套措施。其中，组织措施包括：①增加工作面，组织更多的施工队伍；②延长每天施工时间，采用加班或多班制施工；③加大资源投入，增加劳动力和施工机械数量等。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]