[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51879":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},51879,53,1,"单选题","将工程项目计划累计完成工程量曲线与其实施过程中各检查时点累计完成实际工程量曲线绘制在同一直角坐标系中，进行实际进度与计划进度相比较的方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","横道图比较法",false,{"key":16,"text":17,"correct":18},"B","S曲线比较法",true,{"key":20,"text":21,"correct":14},"C","香蕉曲线比较法",{"key":23,"text":24,"correct":14},"D","前锋线比较法","S曲线比较法是指以横坐标表示时间，纵坐标表示累计完成工程量，进行实际进度与计划进度比较的一种方法。由于在通常情况下按工程进展时间绘制出的累计完成工程量曲线形状像S而得名。在同一坐标系中，将计划S曲线与工程实施过程中各检查时点累计完成的实际工程量曲线进行比较，即可对比分析工程实际进展情况。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]