[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51878":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},51878,53,1,"单选题","工程进度计划执行的跟踪检查中，收集数据的主要方式是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进度计划偏差预测",false,{"key":16,"text":17,"correct":18},"B","工程进度报表和现场实地检查",true,{"key":20,"text":21,"correct":14},"C","专家调查法",{"key":23,"text":24,"correct":14},"D","实际进度与计划进度进行对比","对工程进度计划执行情况进行跟踪检查时，收集数据的主要方式有两种：①工程进度报表。定期收集工程进度报表是反映工程实际进度的主要方式。工程实施单位应按照进度管理制度规定的时间和报表内容，填写工程进度报表，进度管理人员可根据程进度报表的数据了解工程实际进展情况；②现场实地检查。在现场实地检查进度计划的实际执行情况，可以加强进度监测工作，掌握工程实际进度的第一手资料，使获取的数据更加及时、准确。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]