[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51877":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},51877,53,1,"单选题","某工程项目的主体工程可以分解为 A、 B、 C、D四个施工过程，各施工过程的流水节拍均为5周，若施工中分四个施工段组织流水作业，其中 B、C工作之间有1周技术间歇时间，则其流水施工工期是（ ）周。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","21",false,{"key":16,"text":17,"correct":14},"B","30",{"key":19,"text":20,"correct":21},"C","36",true,{"key":23,"text":24,"correct":14},"D","42","由已知条件可知：各个施工过程的流水节拍全部相等，即t1＝t2＝t3＝t4＝5（周）。故该工程宜组织全等节拍流水施工。则： ①取施工段：m＝n＝4（段）。 ②确定流水步距：K＝t＝4（周）。 ③计算流水施工工期：T＝（m＋n－1）K＋∑Z－∑C，式中，∑Z为技术间歇时间之和，∑C为平行搭接时间之和。故流水施工工期T＝（4＋4－1）×5＋1－0＝36（周）。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]