[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51876":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},51876,53,1,"单选题","某工程项目主体工程和装饰工程均可分为四个施工段组织流水作业，其流水节拍分别为4周、5周、4周、4周和4周、3周、4周、4周，则该两个分部工程的流水施工工期是（ ）周。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","15",false,{"key":16,"text":17,"correct":14},"B","16",{"key":19,"text":20,"correct":14},"C","19",{"key":22,"text":23,"correct":24},"D","21",true,"根据已知条件，主体工程和装饰工程都采用流水作业。计算过程如下： ①求各施工过程流水节拍的累加数列。Ⅰ：4 9 13 17，Ⅱ：4 7 11 15。 ②将相邻两个施工过程的累加数列错位相减。Ⅰ与Ⅱ： ③确定流水步距。流水步距等于各累加数列错位相减所得差值中数值最大者，即：KⅠ，Ⅱ＝max（4，5，6，6，－15）＝6（周）。 ④计算流水施工工期：T＝∑KⅠ，Ⅱ＋∑t2j＝6＋（4＋3＋4＋4）＝21（周）。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]