[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51875":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},51875,53,1,"单选题","某工程项目基础工程和主体工程均可分为四段组织流水作业，其流水节拍分别为3周、4周、3周、4周和4周、2周、4周、3周，则两个分部工程之间的流水步距是（ ）周。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","2",false,{"key":16,"text":17,"correct":14},"B","3",{"key":19,"text":20,"correct":21},"C","4",true,{"key":23,"text":24,"correct":14},"D","5","根据已知条件，基础和主体工程都采用流水作业。计算过程如下： ①求各施工过程流水节拍的累加数列。基础工程：3 7 10 14，主体工程：4 6 10 13。 ②将相邻两个施工过程的累加数列错位相减。基础与主体 ③确定流水步距：流水步距等于各累加数列错位相减所得差值中数值最大者，即：K基础，主体＝max（3，3，4，4，－13）＝4（周）。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]