[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51874":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},51874,53,1,"单选题","某工程项目的主体工程和装饰工程均可分为四段组织流水作业，其流水节拍分别为5周、6周、6周、5周和4周、5周、5周、4周，若组织分别流水施工，则其流水施工工期是（ ）周。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","23",false,{"key":16,"text":17,"correct":18},"B","26",true,{"key":20,"text":21,"correct":14},"C","30",{"key":23,"text":24,"correct":14},"D","40","根据已知条件，主体工程和装饰工程都采用流水作业。计算流水施工工期步骤有： ①求各施工过程流水节拍的累加数列。Ⅰ：5 11 17 22，Ⅱ：4 9 14 18。 ②将相邻两个施工过程的累加数列错位相减。Ⅰ与Ⅱ： ③确定流水步距：流水步距等于各累加数列错位相减所得差值中数值最大者，即：KⅠ，Ⅱ＝max（5，7，8，8，－18）＝8（周）。 ④计算流水施工工期：T＝∑KⅠ，Ⅱ＋∑K2＝8＋（4＋5＋5＋4）＝26（周）。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]