[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51872":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},51872,53,1,"单选题","流水施工的工艺参数是指参与流水施工的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工段数",false,{"key":16,"text":17,"correct":18},"B","施工过程数目",true,{"key":20,"text":21,"correct":14},"C","搭接间距",{"key":23,"text":24,"correct":14},"D","技术间歇","组织流水施工，需要在研究工程特点和施工条件的基础上，通过确定一系列流水参数来实现。组织流水施工时，首先应将工程对象划分为若干个施工过程。工艺参数是指参与流水施工的施工过程数目，一般用“n”表示。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]