[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51871":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},51871,53,1,"单选题","某工程项目的基础工程可以分解为挖基槽、砌基础、回填土三个施工过程，各施工过程的流水节拍均为5天，其中砌基础、回填土两项工作之间需要有2天技术间歇时间，若施工段数等于参加流水作业的施工过程数，则其流水施工工期是（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","17",false,{"key":16,"text":17,"correct":14},"B","23",{"key":19,"text":20,"correct":21},"C","27",true,{"key":23,"text":24,"correct":14},"D","30","由已知条件可知：t1＝t2＝t3＝t4＝5（天）。取施工段：m＝n＝3（段）。确定流水步距：K＝t＝5（天）。计算工期：T＝（m＋n－1）K＋∑Z－∑C＝（3＋3－1）×5＋2－0＝27（天）。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]