[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51869":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},51869,53,1,"单选题","某基础工程的土方开挖量为450m3，土方工程的产量定额为1.2m3\u002F工日，要求15天完成，则完成土方开挖的专业工作队人数至少需要（ ）人。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","22",false,{"key":16,"text":17,"correct":18},"B","25",true,{"key":20,"text":21,"correct":14},"C","32",{"key":23,"text":24,"correct":14},"D","36","流水节拍计算公式为：t＝Q\u002F（RS）。式中，t代表流水节拍；Q代表某施工段的工程量；R代表专业工作队的人数或机械台数；S代表产量定额，即单位时间（工日或机械台班）完成的工程量。根据题意，代入公式可得：15＝450\u002F（R×1.2），可计算出R＝450÷（15×1.2）＝25（人）。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]