[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-51868":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},51868,53,1,"单选题","依次施工组织方式的特点是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","单位时间内投入的资源量相等",false,{"key":16,"text":17,"correct":14},"B","能充分利用工作面，缩短工期",{"key":19,"text":20,"correct":14},"C","能提高劳动生产效率",{"key":22,"text":23,"correct":24},"D","施工现场组织、管理比较简单",true,"依次施工组织方式具有的特点包括：①单位时间内投入的资源量较少，有利于资源供应的组织；②每一时段仅有一支专业队在现场施工，施工现场组织、管理比较简单；③没有充分利用工作面进行施工，工期拖得较长；④如果按专业组建工作队，则各专业工作队不能连续作业、工作出现间歇，劳动力和机具设备等资源无法均衡使用；⑤如果由一支工作队完成全部施工任务，则不能实现专业化施工，不利于提高劳动生产率和工程质量。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]